Vankor cluster

The Company continues to establish the Vankor cluster (based on the Vankor field) where Suzunskoye and Tagulskoye fields have come on stream and are being actively developed. Rosneft is also getting ready to launch the Lodochnoye field, thus completing formation of the cluster.

Suzunskoye field
Suzunskoye field
2.1 mmt
of liquid hydrocarbons produced in 2020

Phase 2 of the Suzunskoye field development is underway envisaging the construction of gas facilities (gas treatment unit with a compressor station, the Suzun–Vankor interfield gas pipeline, gas well pads). The Company completed three underwater crossings (2,200 m long in total) by directional drilling and is building the Suzun–Vankor interfield gas pipeline.

Follow-up exploration is ongoing on a new prospective target (Nkh-3 formation). Drilling continues in the field’s southern part.

In 2020, a total of 20 wells were drilled at the field, including seven multilateral ones. Production of liquid hydrocarbons totalled 2.1 mmt.

Tagulskoye field
Tagulskoye field
1.4 mmt
of liquid hydrocarbons produced in 2020

Rosneft continues to build field facilities, well pads, and other infrastructure.

A drilling programme is underway aiming to bring additional reserves into production.

In 2020, we drilled 61 wells, including 33 multilateral ones. Production of liquid hydrocarbons totalled 1.4 mmt.

Lodochnoye field
Lodochnoye field
0.8 mmt
of liquid hydrocarbons produced in 2020

Pilot production continues at the field in the run-up to commercial development.

Production drilling is underway at the most prolific sections by reserves (reservoirs of the Yakovlev suite). Construction and installation work is ongoing at infrastructure and oil and gas treatment facilities to start up key field facilities.

In 2020, the Company drilled 11 wells, including five multilateral ones. Production of liquid hydrocarbons totalled 0.8 mmt.